NAPERVILLE, IL — Maintenance work is expected to close parts of Naperville’s Central Parking Garage starting April 1.

The seven-phase project will include resurfacing sealant on each floor of the three-level parking garage to prevent leakage. Crews will also paint the entire parking garage and coat the rooftop level.

The project’s first three phases will involve part of each of the garage’s levels being closed at a time. The entire top floor will be closed in late June during phase four of the project. The last three phases will close an entire floor of the parking garage at time.

Detour and closure signs will be posted in the facility to help direct traffic. The work is expected to wrap up Sept. 3, if weather permits.